Business news from Ukraine

33 MW SOLAR POWER PLANT OF BUSINESSMAN KHMELNYTSKY TO BE CONNECTED TO SUBSTATION

5 June , 2019  

Podilsky Energoconsulting LLC under a contract with PJSC Zaporizhiaoblenergo will reconstruct the Robocha substation to connect Scythia Solar 2 photovoltaic power plant with a capacity of 33 MW belonged to UDP Renewables of businessman Vasyl Khmelnytsky.
The cost of the contract signed on June 3, 2019 is UAH 20.641 million, according to the ProZorro e-procurement platform.
According to a posting on the website of UDP Renewables, the start of the operation of Scythia Solar 2 photovoltaic power plant is scheduled for September 2019.
The plant is located on the territory of Kostiantynivka rural council of Melitopol district of Zaporizhia region.
As reported, UDP Renewables on March 1, 2019 launched Scythia Solar 1 photovoltaic power plant with a capacity of 13 MW in Zaporizhia region. Investment in the project totaled $10.1 million.
KNESS (Podilsky Energoconsulting LLC is a member of the goup) acted as general contractor and Ukrgasbank (Kyiv) acted as a financial partner.
According to UDP Renewables, its plans include an increase in the 2 photovoltaic power plants portfolio to 175 MW in 2019.

, ,