DMZ upgrades equipment at Sukha Balka mine

26 June , 2025  

Dnipro Metallurgical Plant (DMZ), a part of DCH Steel of businessman Aleksandr Yaroslavsky’s DCH Group, is upgrading equipment at Sukha Balka mine.
According to information in DCH Steel’s corporate newspaper on Thursday, the mine has updated the cage for the Yubileynaya mine. It is specified that the cage is ready for lowering and operation.
“Sukha Balka is the only enterprise in Ukraine that uses three-storey mine cages. Currently, Yubileynaya is preparing to replace the unique hoisting unit, the post says.
“The surfaces of the cage had to be well prepared, cleaned, blown out, and then primed and painted. We painted in two layers. We used special coatings – primer and enamel, which are used for surfaces exposed to aggressive environments. The coating, according to the manufacturer, should reliably protect the surface for about 10 years,” explained Maxim Kopeyka, chief mechanic of the mine.
The mine cage is currently in a disassembled state at the warehouse and is ready for transportation to the mine. The new cage is scheduled to be installed in July.
The Yubileynaya mine cage has a capacity of 15 tons and can accommodate 126 people. It has a service life of 5 years.
In addition, the rolling campaign is scheduled to start next week at Rolling Shop No. 2 at DMZ. The shop has prepared equipment for intensive work during the off-peak period.
DMZ specializes in the production of steel, cast iron, rolled products and rolled products, such as channels and angles, and special profiles for the machine building and mining industries.
On March 1, 2018, DCH Group signed an agreement to buy Dnipro Metallurgical Plant.
Source: https://www.dmz-petrovka.dp.ua

 

,