PJSC Donbasenergo by July 2020 plans to complete the introduction of the single automated system to manage the key assets of Sloviansk thermal power plant (TPP). The company said that the system allows general effectiveness of business management.
The natural obsolescence of the key production assets of the TPP, which celebrated its 65th anniversary last year, leads to an increase in the number of breakdowns, malfunctioning of the equipment fleet and, as a result, expenditure growth.
The implemented module of the plant’s resource management and statistical analysis will help reduce the number of restoration repairs. Based on the available scheduled preventive repairs statistics, the economic feasibility of using equipment is determined, a decision is made to continue the operation of the old equipment or purchase new one, the company said in the release.
Donbasenergo owns Starobesheve (located in the occupied territory) and Sloviansk TPPs with a total installed capacity of 2,880 MW, in particular Sloviansk TPP’s capacity is 880 MW. At the end of March 2017, the generation company announced the loss of control over the operation of Starobesheve TPP, as well as part of structural units located in the temporarily uncontrolled territory.