DTEK Kyiv Grids has completed 40% of repairs to prepare for winter

5 May , 2025  

DTEK Kyiv Grids has completed almost 40% of the repairs planned for 2025 to prepare the city’s energy infrastructure for stable operation during peak consumption periods, in particular during the heat wave or autumn and winter.

“We have already completed almost 40% of the activities planned for 2025. In particular, we have repaired more than 90 transformer substations of different voltage classes and completed more than 300 repairs of cable lines,” the company said, citing Denys Bondar, CEO of DTEK Kyiv Electricity Grids.

In total, in 2025, the power engineers of the transmission system operator plan to carry out repairs at six high-voltage substations, as well as 802 distribution and transformer points. In addition, it is planned to repair almost 60 kilometers of overhead power lines, 60 transformers, 217 switches and carry out 2,150 repairs on underground cable power lines.

As noted in the company, the power engineers of the capital conduct inspections, diagnostics of equipment and electrical lines, in particular, using thermal imagers, mobile electrical laboratories, analysis of technical fluids, etc. and, based on the data obtained, identify weaknesses where an accident may occur.

As reported, last year DTEK Kyiv Electricity Networks repaired and reconstructed 797 power facilities and 62 km of power lines and performed 5 thousand repairs of cable lines, investing almost UAH 1 billion in these projects.

,