The electricity deficit has slightly decreased due to increased production, but remains at a significant level and is still insufficient to cover consumption in full, NEC Ukrenergo said.
“After repairs, two units at thermal power plants returned to the grid. At the same time, one unit was taken out for emergency repairs. Also during almost all day there is the import of electricity from other countries,” described the situation “Ukrenergo” in its daily update in the Telegram channel.
At the same time, according to the system operator, power consumption is gradually increasing due to the intensification of frost, with a more rapid increase expected tomorrow with the beginning of the working week.
The company confirmed the information previously promulgated by the network operators on the introduction of limits of consumption in the regions only for the period from 16:00 to 20:00.
The exceptions are the Kyiv and Odesa regions, where there are network restrictions.
In particular, emergency shutdowns continue in Odessa and nearby areas due to a large-scale accident at one of the substations of Ukrenergo.
The company assured that together with the Odessa regional military administration and the regional energy company its specialists are developing reserve schemes of connecting Odessa and nearby areas, and repair teams of Ukrenergo and the regional energy company are working around the clock to eliminate the consequences of the accident and the quickest resumption of power supply.
As reported, since Sunday morning, in order to avoid accidents due to equipment overload, stabilization shutdowns have been introduced in Goloseevskyi, Solomenskyi and Pecherskyi districts, as well as on the Left Bank of the capital. In the Kiev region, restrictions will be applied in Kiev-Svyatoshinsky district. Due to the accident, there is also temporarily no light in Fastivsky and Vasylkivsky districts of Kyiv region.
On Friday evening and then on Saturday morning a large-scale accident occurred at one of the substations of Ukrenergo, as a result of which Odessa and the Odessa region were out of electricity. According to data as of the evening announced by Herman Galushchenko, head of the Ministry of Energy, one third of consumers were connected to the grid.