Alliance Novobud development company continued active work on its projects in October

In October 2025, the Alliance Novobud development company continued active construction work on the Montreal House project in Kyiv and the Krona Park II and Lesovy Kvartal residential complexes in Brovary (Kyiv region), according to a report on construction progress on the company’s website.

According to the information, in the capital’s Montreal House project (102 Bolshaya Vasylkivska Street/83 Antonovycha Street), plastering work and the installation of cement screed on standard floors and in common areas, as well as facade insulation, continued in blocks 1 and 2 in October. In block 3, electrical cables were laid along the risers of “cold passages” and stairwells. In block 4, the installation of translucent aluminum structures continued (65% complete) and cables were laid along the risers and stairwells.

At the Montreal House parking lot, the waterproofing of the upper slab in the inner courtyard area has been completed, the installation of storm sewer pipes is continuing, and the waterproofing of the stylobate slab on the side of Bolshaya Vasilkovskaya Street has begun. The tower crane has also been dismantled to carry out the next set of works, and a metal frame for the entrance canopy on the side of Antonovycha Street has been installed.

At the Krona Park II residential complex (Brovary, Vasyl Simonenko Street, 32), the insulation of the basement walls was completed in October in building 5, backfilling of the foundation cavities continues, roofing work and installation of PVC windows are underway (windows have been installed from the 2nd to the 10th floors, with work continuing on the 11th and 12th floors). In building 8, the installation of internal water supply and heating engineering networks has begun, the installation of internal power supply and lighting networks is continuing, connection to external heat and water supply networks is being carried out, as well as facade work: section No. 1 is 95% complete, section No. 2 is 75% complete, and section 3 is 45% complete.

In building 9 of Krona Park II, the finishing touches are being made to the common areas and the landscaping of the surrounding area, commissioning work is underway, and the preparation of the documentation package for the completion certificate has begun. In building 10, finishing work has begun in common areas and apartments, and the installation of internal plumbing, electrical, and lighting networks is continuing. In building 12, roofing work has been completed in sections 1 and 2, and the installation of PVC windows is continuing (installed up to the 9th floor of section 1, work is underway on the 10th and 11th floors). In buildings 14 and 16, the pile field has been completed, with 100% of the bored piles installed.

At the Lesovy Kvartal site, building No. 16 (Brovary, V. Chornovola Street), vertical monolithic structures were erected in sections 2.2, 2.1, and 1 in October, and work began on the construction of brick walls.
The company specifies that work on the sites in Kyiv and Brovary is at different stages – from the pile field and monolith to the finishing touches and preparation for commissioning, while the developer is keeping to the schedule and continuing to move the projects towards completion in stages.

Alliance Novobud is a development company that has been operating in the residential real estate market of Kyiv and the Kyiv region for over 18 years. The developer specializes in comfort+ and business-class projects, with key projects including Montreal House and Illinsky House in Kyiv, as well as Krona Park II, Lesovy Kvartal, Zeleny Kvartal, Madison Gardens, and Lavandovy in Brovary.

According to industry ratings, Alliance Novobud was among the top 20 largest developers in Kyiv and the region in terms of the number of apartments completed in 2024 (481 apartments in five buildings, with a market share of about 2.2%). The company is a winner of the UKRAINIAN SPECIAL BUILDING AWARDS IBUILD and Business of the Year professional awards, and was named “Developer of the Year” and “Residential Complex of the Year” for the Montreal House and Krona Park II projects.

 

, , ,

Sales of apartments in final building of Lisovy Kvartal residential complex have begun in Brovary

The Lisovy Kvartal residential complex in Brovary is entering a new stage of development with the start of sales of apartments in the final building. The complex is positioned as comfortable housing close to a green area and the developed infrastructure of the city center. The final phase implements the best solutions and standards that have ensured the success of the entire Lisovy Kvartal complex: functional layouts, high-quality materials, modern construction technologies, and attentive consideration of the needs of future residents.

Real estate sales are conducted according to the MON (future real estate object) mechanism. MON is a part of a divisible object of unfinished construction, which, after commissioning, will become an independent real estate object, for example, an apartment, garage, or commercial premises. Investments in FPO are registered in electronic systems and protected by law, so the buyer receives property rights to the selected part of the property even before the completion of construction.

Advantages of FPO for buyers:

  • acquisition of property rights to the object even before the completion of construction;
  • registration of transactions in state electronic systems;
  • price fixation at the time of conclusion of the contract;
  • increased security and risk control.

The complex is located in the central district of Brovary, just 15 minutes from the Lisova metro station and important transport hubs of the capital. A reliable monolithic frame structure was used for the construction of the final building, which guarantees durability, fire resistance, and resistance to seismic activity.

There is a modern kindergarten on the territory of the complex, and nearby is the largest city park and a picturesque pine forest, which create a comfortable environment for families to live in.

Various types of apartments are available for sale: from one-room apartments (approximately 40 m²) to spacious family options (up to 100 m²). The construction is being commissioned by MTDK BUDIVELNE MISTO LLC in partnership with Alliance Novobud.

The sales office at 8A V. Chornovola Street, Brovary, tel. +38 (044) 344-08-23, is already scheduling appointments with buyers and providing detailed information about available layouts, purchase terms, etc.

 

, ,

Booking of apartments in final building of Lesniy Kvartal residential complex has started!

The developer Alliance Novobud opens a new stage in the history of the legendary Lesniy Kvartal residential complex – the first applications for the purchase of apartments in the final building have been accepted.

Construction work is already underway: the pile field has been completed, 100% of the bored-injection piles have been installed, the concreting of the foundation slab of section No. 2.2 has been completed, and work is underway to reinforce and concrete the basement walls. At the same time, the foundation slab of section No. 1 is being prepared for installation and two tower cranes have already been installed.

The final building of the Lesniy Kvartal residential complex in Brovary consists of 3 sections with variable number of storeys, 567 apartments with well-thought-out and comfortable layouts, a private adjoining territory with two ground parking lots, a playground and designer landscaping.

Don’t miss the opportunity to become a part of the legendary “Forest Quarter” in the heart of Brovary – book the best units at prices that will not be available anymore! Moreover, every current customer can become a member of a special referral program. For all the details, please contact the sales office: 8A, V. Chornovil str., Brovary, tel. +38 (044) 344-08-23.

 

,