PJSC “Kyivmiskbud” Holding Company contributed 81,364,000 UAH to the state and local budgets between April 1, 2023, and March 31, 2026, the company’s press service reported.
“Kyivmiskbud” once again demonstrates transparency and financial discipline. Even under challenging anti-crisis conditions, the company remains a conscientious taxpayer. We operate transparently, comply with legal requirements, and are systematically moving forward,” said Yuriy Tykhonovych, acting chairman of the holding company’s board of directors.
From July 8 to August 18, 2026, “Kyivmiskbud” underwent a scheduled on-site audit by the Main Directorate of the State Tax Service in Kyiv. The audit examined compliance with tax, foreign exchange, and other laws for the period from April 1, 2023, to March 31, 2026, as well as the timeliness of payments of the unified social contribution (USC) from July 1, 2021, to March 31, 2026. A corresponding report was drawn up based on the results of the inspection.
During the specified period, “Kyivmiskbud” paid 81,364,000 UAH to the state and local budgets, of which land rent amounted to 28,086,000 UAH; Unified Social Contribution (USC) – 20,830,000 UAH; personal income tax (PIT) – 17,764,000 UAH; land tax – 6,143,000 UAH; real estate tax – 5,199,000 UAH; military levy – 3,304,000 UAH; income tax – 34,850 UAH.
At the same time, late payment of land rent for 2023 in the amount of 647,800 UAH was identified, the company’s losses for the reporting period were reduced, and additional income tax for the third quarter of 2023 in the amount of 1,833,000 UAH was assessed.
As previously reported, Kyivmiskbud’s balance sheet includes 24 construction sites where more than 120 residential buildings at various stages of completion have been erected. The total area of unfinished construction exceeds 548,000 square meters. The developer began restoration work in March 2026 at a number of sites. In July, the “Podol Grad” residential complex was commissioned. Five more projects are at an advanced stage of completion (the “Freedom” residential complex, the “Twin House” residential complex, the “Oberig-2” residential complex (Building 1), the “Rainbow” residential complex, and the “Gvardeysky” residential complex).
Active construction and installation work is underway at four additional sites.
Kyivmiskbud Holding Company was established in 1994 on the basis of the assets of the state-owned municipal construction corporation “Kyivmiskbud” by consolidating controlling stakes in 28 enterprises and other assets into its authorized capital. It comprises 40 joint-stock companies in which the company holds shares, as well as six subsidiaries and 51 companies with associate member status.
According to data from the National Securities and Stock Market Commission (NSSMC), the Kyiv City Council is the majority shareholder of Kyivmiskbud Holding Company PJSC.