Kyiv Plans to Provide Backup Heating to 80% of Homes in Darnytsia Thermal Power Plant Service Area by End of Year

23 November , 2026  

According to Interfax-Ukraine, Kyiv is accelerating the construction of backup boiler houses designed to provide heat to homes in the service area of the city’s Darnytsia Thermal Power Plant in the event it is damaged by Russian attacks, said Ivan Fedorov, head of the Agency for Infrastructure Restoration and Development.

“Construction is underway on six backup heat supply facilities in the Darnytsia CHP plant service area. Some are already in the final stages, but connecting them to the grid and commissioning them still lie ahead. The goal is to ensure that 80% of homes can be supplied with backup heat by the end of the year,” he reported on his Telegram channel.

As for the Kyiv Region’s energy protection projects, as previously reported, the readiness rate stood at 55% as of mid-November. On October 13, the Kyiv Regional State Administration initiated the transfer of these facilities to the Agency for Restoration. The State Audit Service is involved in the audit.

“We are ready to complete the unfinished protective structures at the substations. The ministry’s decision on the transfer is already in place; we are awaiting the relevant documents from the Kyiv Regional State Administration. Next steps include an audit, selecting contractors, and completing construction,” Fedorov said.

According to his assessment, depending on the readiness of the facilities, the work could take anywhere from three weeks to four months.

Fedorov also noted that within the agency itself, following the completion of audits of regional services, significant discrepancies in operational efficiency, unrealistic construction schedules, and the absence of a unified system for operational oversight were identified.

“Now every facility is under digital monitoring. We can see the actual readiness, funding, pace of work, and any issues. This allows us to avoid delays and respond to risks in advance,” he noted.

Among the priority projects, he also highlighted preparations for the coming winter and infrastructure projects.

“We’re starting right now. The full construction cycle for protecting energy facilities takes six to eight months. Therefore, decisions that will affect the next heating season must be made today… We are monitoring winter road maintenance while simultaneously preparing repairs for next year and bridge construction,” he said.

, , , ,