Business news from Ukraine

Business news from Ukraine

“Avtostrada” resumes construction of subway to Vynohradar

Avtostrada Group of Companies has resumed construction of the subway to the Vynohradar residential area in Kyiv, its press service has reported.
According to the press release, the construction of the Syrets-Pechersk (“green”) line is underway from the Syrets station. In total, the construction of two stations is planned – Mostytska and Prospekt Pravdy.
The section from Syrets station to Mostytska station will be laid in a closed way – by tunneling, and from Mostytska to Pravdy Avenue – in an open way.
The total length of the construction (from Syrets station to Pravdy Prospekt) is 3.78 km.
Atostrada continues construction of a two-tiered rectangular monolithic tunnel on the Mostytska – Pravdy Prospekt section. This design is due to the specifics of the infrastructure of a densely built-up residential area. A pit is being developed and a support system is being installed for further tunnel construction. A PVC membrane waterproofing system is being installed in the concrete areas left by the previous contractor, which can be restored even after the facility is commissioned. As noted, such waterproofing was used during the construction of a section of the tunnel between Lybidska and Demiivska metro stations. The finished sections of the tunnel are being backfilled with soil.
The facility includes six construction sites. Preparatory work is underway at other construction sites.
As the press service emphasizes, Avtostrada started the construction of the metro line to Vynohradar using its own working capital, without advances.
As reported, in August 2024, the Kyiv Metro utility company signed an agreement to continue construction of the Syretsko-Pecherska line in the direction of the Vynohradar residential area. The winner of the tender was Avtostrada Group LLC. The term of the works is set at 30 months and their cost is UAH 13 billion 785 million. The procurement was conducted on the Prozorro electronic public procurement platform.
According to the Kyiv City State Administration, the right turnaround tunnel has already been built with a length of almost 1,250 meters from Mostytska station to Syrets station. In addition, the construction of the main structures of the distillation ventilation unit has been completed. The wall-in-soil method of enclosing structures and the metal structures for the pit have also been partially installed. The main structures of the combined traction substation were constructed, and two-tier tunnels were partially constructed.
In December 2023, Kyiv Metro terminated the contract with Kyivmetrobud JSC in court due to the failure to meet the deadlines for construction work. The court is considering the recovery of a part of the prepayment, the use of which is not confirmed by the relevant acts of work performed, as well as penalties.

, , ,

“Kyiv Metro” has signed contract with Avtostrada for construction of subway to Vynohradar for UAH 13.8 bln

Kyiv Metro has signed a contract to continue construction of the Syretsko-Pecherska subway line in the direction of the Vynohradar residential area, with Avtostrada Group LLC winning the tender.

According to the website of the Kyiv City State Administration, the construction period is set at 30 months and the cost of the works is UAH 13 billion 785 million. The procurement was conducted on the Prozorro public procurement platform.

“We are currently in the process of obtaining all the permits required by law and handing over the construction sites to the contractor. After that, construction work will begin,” the statement said.

The city administration emphasized that the construction of the subway will not only solve transportation problems, but will also provide residents of the Podil district with “round-the-clock reliable shelters.”

According to the Kyiv City State Administration, the right-hand tunnel has already been built, stretching almost 1,250 meters from Mostytska station to Syrets station. In addition, the construction of the main structures of the distillation ventilation unit has been completed. Also, the wall-in-soil method of enclosing structures and the metal structures for the pit have been partially installed. The main structures of the combined traction substation were constructed, and two-tier tunnels were partially constructed.

In December 2023, Kyiv Metro terminated the contract with Kyivmetrobud JSC in court due to the failure to meet the deadlines for construction work. The court is considering the recovery of a part of the prepayment, the use of which is not confirmed by the relevant acts of work performed, as well as penalties.

, , , ,

“Avtostrada” wins tender for construction of metro to Vynohradar

Avtostrada Group of Companies has been recognized as the winner of the procurement procedure for the construction of the metro in Vynohradar, its founder Maxim Shkil said.
“We will start work without advances, at the expense of our own working capital. For us, the decision to enter the metro construction market is strategic, the company has been preparing for this for 3 years,” Shkil wrote on Facebook.
According to the public procurement platform Prozorro, the winner of the tender was determined on July 12 with a price of UAH 13 billion 785 million, which is slightly lower than the stated expected cost of the purchase of UAH 13 billion 956 million 843 thousand 711.13. The decision can be appealed until July 18.
The terms of the procurement stipulate the completion of construction (5th and 6th launch complex) of the Syretsko-Pecherska subway line to the Vynohradar residential area by December 30, 2026.
Shkil said that before the start of work, a detailed analysis of the status of work performed by previous contractors is required. Next, it is necessary to compare the actual amount of work performed and those that should be performed in accordance with the existing design solutions. After that, it is necessary to adjust the project in terms of the scope, type of work, and cost.
“For this purpose, Avtostrada has its own design institute with a separate underground construction unit, where employees have considerable experience in metro design. Accordingly, we will start this stage of work immediately,” said the founder of the group of companies.
In parallel with the documentary work, it is planned to start the construction of the metro to Vynohradar in the coming months.
He noted that there are difficulties with organizing the construction process at the highest possible pace, i.e. nine construction sites with round-the-clock operation.
“In today’s realities, it is impossible to ensure such an approach from the very first days, as the subway construction industry has been practically lost over the past ten years. From the very first days, Avtostrada will engage its employees, and in parallel, to reach the maximum construction schedule, we will recruit and train personnel, which will actually revive the metro construction industry,” said Shkil.
According to him, a significant factor that will affect the pace of construction is timely funding from the state for the work.
“We set ourselves the task of reaching the full pace of work around the clock in all construction sites in 2025, provided that we have adequate funding. In total, we plan to employ more than 4000 people. The total investment in this project will be more than $50 million. Next month, the company plans to contract the necessary equipment for the construction of the subway for more than $30 million. In addition, to avoid construction interruptions, we are counting on loans and our own working capital of up to UAH 1 billion. – These funds will be used in case the customer has a delay in financing. This will allow us to cover short cash gaps and continue to operate,” Shkil said.
As reported, on May 13, Kyiv Metro announced a tender for the continuation of the construction of the Syretsko-Pecherska line towards the Vynohradar residential area with a total cost of UAH 13,956 million.
In December 2023, Kyiv Metro terminated the contract with Kyivmetrobud JSC in court due to unsatisfactory terms of construction works performed by the contractor. The claim also seeks to recover a portion of the prepayment, the use of which was not confirmed by the relevant acts of completion. As of May 2024, the facility has constructed a right distillation tunnel with a length of almost 1,250 meters from Mostytska station to Syrets station, and completed the construction of the main structures of the distillation ventilation unit. Also, the wall-in-soil method of enclosing structures, monolithic and reinforced concrete support of the pit with metal structures – with excavation and removal of soil – were partially installed; the main structures of the combined traction substation were built; two-tier tunnels were partially constructed, etc.

, , , ,

TOP MANAGERS OF KYIVMETROBUD READY TO COOPERATE WITH LAW ENFORCERS TO BUILD SUBWAY LINE TO VYNOHRADAR

Top managers of PJSC Kyivmetrobud, acting as a contractor general in the project to extend the Syretsko-Pecherska subway line in Kyiv’s subway, is ready to cooperate with law enforcement authorities in order to continue construction works, Director General of PJSC Kyivmetrobud Kostiantyn Saliy said at a press conference at Interfax-Ukraine on Wednesday.
“The owners of Kyivmetrobud unanimously appointed me as director general, so that the previous director, Mr. Metelytsia, could deal with what he is directly doing – the construction of the subway. Political, media and team reorganization issues will be led by the director general,” Saliy said.
According to him, the enterprise will conduct an inventory of material and technical assets, as well as turn to law enforcement authorities regarding the likely embezzlement of funds.
“At the moment, the Prosecutor General’s Office has decided to seize accounts. They are also developing a “recipe” on how to control the distribution of these funds transparently. We believe that it’s good that the Prosecutor General’s Office will be present and observe how the work is being done. The Prosecutor General’s Office will also have access to documents, [will see] where the funds went, what work was done, who signed papers with margins, and will identify the whole range of interested parties,” Saliy added, noting that resolving the situation around the enterprise depends on law enforcement authorities.
As reported with reference to the press service of the Prosecutor General’s Office, the investigating judge of Kyiv’s Pechersky district court seized money in the bank accounts of PJSC Kyivmetrobud and its branches.
“In the future, the Prosecutor General’s Office will appeal to court with a motion to transfer these funds to the ARMA [Asset Recovery and Management Agency] with the possibility of making payments to build the subway under control of the state,” the press service said.
Oleh Tokarev, the head of the Kyivmetrobud’s supervisory board, said at the press conference at Interfax-Ukraine that the reason for the change in the company’s management is the unsatisfactory pace of subway construction towards the Vynohradar area, due to which the launch of the subway line is postponed for a year.
“The amount of the tender is UAH 6 billion. At the end of the year, an advance payment of UAH 2.6 billion was received. During the year that we lived with Director General Vasyl Kobil, UAH 1 billion was spent and work for UAH 150 million was completed but not signed by the customer. “This is only 2.5% of the contract amount. Therefore, on December 17, the supervisory board decided to dismiss Kobil and appoint Oleksandr Metelytsia to the post of director general,” he said.
In turn, Managing Partner of the Ilyashev & Partners law firm Mykhailo Ilyashev said that a “series of myths” about the seizure of the enterprise are being spread and suggested that “the problem was inspired by the former head.”
He also commented on the statement of the Justice Ministry on the reinstatement of the director of PJSC Kyivmetrobud and making appropriate changes to the public register.
“The minister did not annul anything. He did not cancel any decisions of the supervisory board and could not cancel, because this is outside the competence of the Justice Ministry. Most likely, this was about the conclusions made by the commission under the Justice Ministry that the notary who made changes to the register made a technical error. Today, these documents will be submitted to the notary so that the relevant changes are introduced again,” Ilyashev said, emphasizing that the statement of the ministry does not cast doubt on the lawfulness of the decisions of the supervisory board.
As reported, in 2018, Kyiv Metropoliten entered into an agreement on construction work to extend the Syretsko-Pecherska subway line with Kyivmetrobud, which won the tender held on the ProZorro platform.
As part of the first phase of work, it is planned to build two stations, Mostytska and Prospekt Pravdy, at a section of almost 4 km, and branches to the Vynohradar station to extend the line.
It was planned that the work will last until 2021, and its cost will be UAH 5.993 billion.

, , ,

DEADLINE FOR LAUNCHING METRO TO VYNOHRADAR POSTPONED FOR A YEAR

The deadline for completing construction work to extend the Syretsko-Pecherska line of Kyiv Metropoliten is postponed for a year, Oleh Tokarev, the head of the supervisory board of PJSC Kyivmetrobud, the project’s general contractor, has said at a press conference at Interfax-Ukraine. “The deadline has been disrupted for one year. The launch is postponed for a year,” he said.
“I think it [construction according to the schedule] won’t be completed. Today, the lag is not less than 7-8 months,” Yevhen Shataikin, the chief engineer for the construction of subway to Vynohradar, said.
According to him, currently the work is not carried out in full.
“Since Oleksandr Metelytsia had been actually moved away from solving problems, a systematic non-fulfillment of the schedule began. We were set aside from the process of purchasing equipment. The equipment that was purchased today does not work in full with the speed we foresaw. We are falling behind schedule,” he said.

, ,